DAY2: Setting out
- pulethabang733
- Sep 27, 2022
- 1 min read
We spent most of the morning setting out and marking out site boundaries on which house boundaries would be marked.


Then we later marked out were we will dig the trenches and we tested the soil before the trench excavations can be done. The afternoon was busy. We did the digging of the foundations trenches but, the TLB have already dug so we just dug to widened the trenches and dig deeper according to required depth of the foundations and strip footings.
We did that for the rest of the evening until we left. we were tired because of the labor that day but we enjoyed ourselves and learned a lot about the foundations and their sequence of construction.
Reported by Pule